Scheduled maintenance

Cloud Performance 2024 hardware replacement

From 17/11/2024, 10:00 to 17/11/2024, 11:00

Affected components : Virtual servers (Under maintenance), 🇫🇷 Paris-Magny (PAR) (Under maintenance)

  1. Completed

    The maintenance was carried out successfully and is now complete.

    VPS downtime was limited to 9 minutes (from 10:20 to 10:29).

  2. In progress

    Maintenance is now in progress

  3. Scheduled

    START DATE: November 17, 2024

    START TIME: 10:00 AM (CET)

    END DATE: November 17, 2024

    END TIME: 11:00 AM (CET)

    SERVICES: Cloud Performance 2024 Architectures (AMD RYZEN 9900X)

    MAINTENANCE PURPOSE: Hardware component replacement on Cloud Performance 2024 architectures (AMD RYZEN 9900X).

    MAINTENANCE DESCRIPTION: As part of our continuous service improvement, we will proceed with the replacement of hardware components on Cloud Performance 2024 architectures. This operation requires physical servers to be powered down to allow for component upgrades.

    SERVICE INTERRUPTION RISK: During this maintenance operation, a 15-minute service interruption is expected, during which virtual machines will be stopped and restarted.

    FOR ADDITIONAL INFORMATION: At any time, you can contact us for any information related to this operation through our support team via your customer portal. We thank you for your understanding and apologize for any inconvenience this may cause.